Also, calculate the Average resource size and Productivity of the software for Organic project type.Īns : Given estimated size of project is: 300 KLOC For OrganicĮffort (E) = a*(KLOC) b = 2.4*(300) 1.05 = 957.61 MM ![]() Calculate the Effort, Scheduled time for development.